Sahi, is responsible for the supply, installation and commissioning of totally new TV station located in Erbil, Iraq.

The project started in January 2019, and in less than 3 months, one warehouse and 3 building units were successfully converted into brand new TV station facility thanks to in-house architect department and interior designers of Sahi.

The Project

As well as three large multi-camera studios (800m2, 800m2 and 600m2), three studios include 8 TV sets, 4 post-production edit suites, PCR, MCR and graphics.

The system room comprises 15 equipment racks containing all the central broadcast and core IT hardware. All equipments and infrastructures were supplied and installed by Sahi.

Sahi had a challenge to meet the delivery date of the end of March. 

By mid-March 2019, Sahi had delivered all technical areas, and the main areas had been tested ready for User Acceptance Testing by the client.